Experience

4M Storm: TCS – Irma Service Highlights

  • Project, Data Hub, TDMS (ADMS) System Management
  • Project forecasting and reporting to President and area Supervisors
  • Data management, audit and verification
  • Customer and contractor setup and configuration
  • Personnel/HR – Candidate interviewing, onboarding, safety and systems training
  • Check routing and delivery including daily time management and verification

Field and Device Services

  • Debri Monitoring, Debri Monitor Supervision and Truck Certifications
  • Handheld Devices – Cellular and printers
  • Software installation, configuration and cellular activation
  • Daily service and troubleshooting, utilization and inventory management
    Electro-Mechanical/repair
  • Mobi remote support, bluetooth, wireless networking, DMZ, VPN and cellular networking

Custom Process Development and Implementation including in-field process
deviations.

US Army Corps of Engineers – Alabama Tornado Recovery
Date of Work: 5/8/2011 – 10/8/2011
Duration: 6 Months
Size of Project – 5.1+ Million Cubic Yards
Project Description: Operate ADMS ticketing for Right of Way and Right of Entry debris removal throughout the state of Alabama including 35+ task orders. Provide specialty ticketing for Stump & Leaner/Hanger Removal which includes GPS & picture documentation of each. Operation highlights include:

  • Operated 50 Disposal & TDSR sites throughout the state
  • Processed over 5.1+ Million Cubic Yards – 3 Month Period
  • Processed 19,115 Stump tickets
  • Processed 50,609 Leaner/Hanger tickets
  • Checked-In 3,130 Hauling Units & 1,370 Support Equipment
  • Check-In 4,730 Personnel
  • Hired over 75 local Field Tech Support personnel

Download PDF Project Information Sheet

Weston Solutions – Joplin Tornado Recovery
Date of Work: 6/2/2011 – 7/24/2011
Duration: 2 Months
Size of Project – 1.27+ Million Cubic Yards
Project Description: Operate ADMS ticketing for Right of Way debris Removal City of Joplin, City of Duquesne, Jasper County, and Newton County, MO. Provide specialty ticketing for Stump and Leaner/Hanger Removal which includes GPS & picture documentation of each. Operation highlights include:

  • Operated 4 Disposal & 1 TDSR sites
  • Processed over 1.27 Million Cubic Yards
  • Checked-In 1,163 Hauling Units & 498 Support Equipment
  • Operated up to 99 Handheld devices
  • Utilized 10 locally Joplin hired Field Tech Support personnel

Download PDF Project Information Sheet

H20 Consulting – Mississippi Tornado Recovery
Date Work Completed: 5/31/2011 – Work On-Going
Duration: 2-3 Months
Size of Project: 93,000+ Cubic Yards
Project Description: Operate ADMS ticketing for Right of Way debris removal Webster and Choctaw County Mississippi. Provide specialty ticketing for Stump Removal which includes GPS & picture documentation of each. Operation Highlights:

  • Operated 2 TDSR sites
  • Processed 90,000+ Cubic Yards
  • Operated 4-6 Handheld Units
  • Operated ADMS for small local contract at cost effective rate

Download PDF Project Information Sheet

BIS Services, LLC-LPV109 Levee Widening
Date Work Completed: 6/1/2010
Duration: 6 Month
Size of Project – 1 Million Tons Sand
Project Description: Operated multiple scale ticketing systems from quarries and borrow sources to track sand and clay materials being placed on LPV109 Levee in New Orleans, LA. Utilized barcoded scaled tickets and remote handhelds on levee to verify load receipts and placement date & time on levee.

Phylway Construction – WBV 15A.2 Lake Cat Levee
Date Work Completed: 12/31/10
Duration: 12 Months
Size of Project – 680,000 Cubic Yards of Clay
Project Description: Operated Truckscale software to track outbound trucks hauling clay to WBV-15A.2 Lake. Utilized handhelds with barcode scanners to track and verify receipt of incoming material onto levee.